Cold Rolling

Wastewater treatment system for the Baosteel Stainless Steel Co. Cold-Rolling Stainless Steel Mill

This wastewater treatment plant is located to the north of the main cold rolling plant building, occupying a total area of 134m¡Á60m. The wastewater is discharged through a wastewater pipe channel for each process production line to the wastewater treatment plant.
The wastewater treatment plant is designed to separately treat the various wastewaters produced from each steel making process system. The wastewater can be divided into 5 main wastewater streams containing neutral salt & chromium, acid, concentrated alkaline & emulsion, diluted alkaline & oil, and finishing wastewater. This project is divided into two construction phases with the total discharge of wastewater in both phases shown as follows:

Wastewater

Wastewater flowrate (m3/h) phase one phase two reserved

Total flowrate

75

265

290

Neutral salt & chromium

10

25

30

Acid

65

110

120

Concentrated alkaline & emulsion

0

18

18

Diluted alkaline & oil

0

110

110

Finishing waste

0

12

12

Phase one wastewater treatment plant
chromium wastewater: 30m3/h
acid wastewater: 120m3/h
Sludge treatment: installed two filter presses during phase one, and one filter press during phase two.
The waste water containing neutral salt and chromium is first treated with waste acid or NaHSO3 to reduce the Cr6+ to Cr3+, and then mixed with acidic wastewater for further treatment.
Acidic wastewater is first treated by aeration to oxidize Fe2+ to Fe3+; then lime is used as a neutralizer to form hydroxide metal participates.
All imported equipment for the phase one project has been? in operation since Aug 27, 2007 and meets the discharge standards shown below:

pH 6-9 SS£º ¡Ü50mg/L
Total Ni: ¡Ü1mg/L Cr6+£º ¡Ü0.5mg/L
Total Cr: ¡Ü1.5mg/L fluoride ¡Ü10mg/L
Oil: ¡Ü5mg/L CODcr: ¡Ü100mg/L
BOD5: ¡Ü 30 mg / L anionic surfactant: ¡Ü10mg/L

Phase two wastewater treatment plant
Phase two wastewater treatment plant is now the design stage for concentrated alkali emulsion, diluted alkali oil, and finishing wastewater treatment system, the treatment capacity are as follows:?
concentrated alkali emulsion£º18m3/h
diluted alkali oil£º 110m3/h
finishing wastewater£º 12m3/h
The wastewater is mainly treated with ultra-filtration, CAF, bio-treatment, and MRB, all equipments and measuring devices will be imported, the treated wastewater is anticipated to meet the follows standards:

PH£º 6¡«9 SS£º ¡Ü50mg/L
Total Ni: ¡Ü1mg/L Cr6+£º ¡Ü0.5mg/L
Total Cr£º ¡Ü1.5mg/L fluoride£º ¡Ü10mg/L
Oil£º ¡Ü5mg/L CODcr£º ¡Ü100mg/L
BOD5£º ¡Ü30mg/L anionic surfactant£º¡Ü10mg/L


In conclusion


MEEG is responsible for the process flow, the automation and other basic to detail designs, purchasing all equipment, installation, commissioning, and etc. Following the Ningbo Baoxin Stainless Steel Co and Jinan Iron and Steel Co., this project is another large scale steel mill wastewater treatment system project for our company; it is also one of our milestones in steel mill wastewater treatment industry.

 

 

Copyright © 2008 McWONG ENVIRONMENTAL & ENERGY GROUP
Shanghai, China Suite 1001 Jintao Building 1900 Shang Cheng Road, Pudong Shanghai 200135 P. R. China
TEL: 021-68552275 FAX: 021-68552276 SERVICE: 021-68536670 Email: info@meeg.com.cn